WESTERN SPRINGS – The village of Western Springs reported that repairs to the
interior of the reverse osmosis plant from the July 31 accident have been
completed. To learn more about the repairs, read the full press release
below.
Repairs to the interior of the plant from the July 31st incident
have been completed and treatment equipment for well #4 was brought back online
this afternoon and is going to distribution. Start up was slightly delayed from
this morning because the system had to be purged of air before reestablishing
output through the LPRO system.
The completion of the Clean-In-Place
(CIP) process for well #3 is expected within the next 1-2 days and the well #3
RO system is expected to be back online late this week or early next week
assuming the CIP process is complete.